When to Start a Desert Remodel: A Calendar

The desert year has a rhythm unlike that of any other place I have worked. The season runs from about October to April. Owners leave in May, the heat arrives, and for four months the valley belongs to the contractors. Almost every substantial remodel is built in that window, which means that everyone wants the same tradesmen at the same time.

The question I am asked each spring is whether a house can be remodeled this summer. The honest answer, by April, is usually no. Here is the calendar I recommend, working backward from a return in the fall.

October to December: decide and engage

This is the moment to begin. You are in residence, the house’s shortcomings are before you daily, and there is time to think. Engage your designer, agree the scope and budget, and have the house measured. If structural changes are contemplated, an architect or engineer should be brought in now.

January and February: design

The design is developed and settled: plans, elevations, kitchen and bath layouts, lighting, and the principal materials. Decisions made now cost nothing to change. The same decisions changed in July are expensive.

February and March: approvals and pricing

In a gated community, the application goes to the architectural committee. Building permits are applied for where required. Contractors price the work from completed drawings, which is the only way to obtain figures that can be compared. I have described the approval process in Remodeling in a Desert Country Club.

March and April: order

Long-lead items are ordered as soon as approval is in hand. Custom cabinetry, windows and doors, stone slabs, appliances, plumbing fittings and lighting can take three or four months to arrive. If they are ordered in June, they arrive in October, and the house is not ready.

Furniture made to order should be commissioned in this period as well.

May: handover

You leave. The house is cleared or protected, and the contractor takes possession. Demolition begins.

June to September: construction

The work proceeds through the heat, generally with early starts. Regular site visits and reports with photographs keep absent owners informed. Questions will arise, and prompt answers keep the program moving.

September and October: finish and install

Painting and final fitting are completed, the house is cleaned, and furniture, rugs, curtains and art are delivered and placed. I aim to hand over a finished house, with beds made and lamps lit, before the owners return.

What can be done in less time

Not every project needs a year. Work that involves no construction can be done far more quickly.

  • Furnishing and decoration can be done in three to five months, depending on how much is made to order.
  • Painting, lighting improvements and window treatments can be completed in a few weeks and need not wait for summer.
  • A single room, such as a primary bedroom or a study, can often be completed during the season with little disturbance.

If you have just bought

Many houses change hands in the spring, at the end of the season. A buyer who closes in April and wants to remodel that summer must move very quickly, and should engage a designer before closing if possible. A more comfortable course is to make modest improvements at once, such as paint, lighting and bedding, to live in the house for a season, and to remodel the following summer with the benefit of knowing it.

New construction

A new house runs to a longer program, commonly two years or more from first sketches to occupation. The designer should be engaged alongside the architect, so that the interiors and the building are conceived together.

The short version

For a summer remodel, begin the previous fall. It sounds early, and it is what allows a calm project in place of a hurried one.

If you are in the valley this season and thinking about next summer, now is the moment. A consultation will establish what the house needs and how long it will take, and you may arrange one through the contact page.