A house inside the gates of a private club is not entirely one’s own to alter. That is part of what one buys: an assurance that the neighbor will not paint his house purple or run a jackhammer through January. It also means that a remodel begins with paperwork, and that the paperwork deserves as much care as the design.
Who decides what
Three authorities may have a say. The first is the property owners association, through its architectural committee, which administers the community’s covenants and design guidelines. The second is the city, or the county in unincorporated places such as Bermuda Dunes, which issues building permits. The third, in some cases, is a historic preservation board, where a house is of recognized significance.
As a general rule, anything visible from outside requires the association’s consent: additions, windows and doors, roofing, exterior colors, walls, pools and landscape. Purely interior work may not, though many associations still wish to be told, and all of them regulate contractors, working hours, parking and deliveries.
An example: Eldorado
The rules differ from club to club, so let me take one whose guidelines are published. At Eldorado Country Club, the property owners association requires written approval from its Architectural Committee before construction, remodeling, alteration or additions. The same applies to installing, replacing or remodeling a pool, spa or water feature.
A major project there passes through five stages:
- An orientation session
- Conceptual design review
- Preliminary plan review
- Final plan review
- Construction verification and completion
Two further points are worth noting. If the work changes from the approved plans, the change must be approved before it is begun. And construction personnel may work only on the site itself, and may not use a neighboring lot without that owner’s written permission.
None of this is unreasonable. It simply takes time, and the time must be planned for. Other clubs have their own procedures, and you should always obtain the current documents for your own community.
The calendar
In the desert, most owners are away in summer, and that is when associations prefer noisy work to be done. The practical consequence is that design and approvals must be completed in winter and spring if construction is to start in late spring and finish by the fall.
Working backward from a November return, a substantial remodel wants its design settled by February and its application lodged soon after. Materials with long lead times, such as stone, custom cabinetry, windows and doors, should be ordered the moment approval is received. Owners who begin thinking about a summer remodel in May are usually thinking about the following summer.
What a good submission contains
Committees are made up of residents, often with an architect advising them. They respond well to applications that are complete and clear. I include measured drawings of the existing house, drawings of what is proposed, elevations wherever the exterior changes, material and color samples, and a short written description that answers the obvious questions before they are asked. A complete submission is seldom sent back. An incomplete one almost always is, and each round costs weeks.
My advice
Read the covenants before you buy, if you can, and certainly before you design. Ask the association office for the current guidelines and fee schedule. Engage your designer early enough that approvals are part of the plan and not an obstacle discovered halfway. And treat the committee as an ally. Its members want the community to look its best, which is, after all, what you want for your own house.
If you are considering work in one of the valley’s clubs, our notes on each community are gathered on the Coachella Valley page.
More from the journal
Private Consultation
Kenneth Bordewick, Principal Designer
Indian Wells Interiors
Phone: (310) 570-3982
Email: kenneth@bhli.us